Construction Updates
Structural Steel:
- Shelf angle installation
- 4th floor, wall installation
Mechanical:
- Ground floor, installation of sanitary lines
- 2nd floor, installation of sanitary lines
Electrical:
- 2nd floor, rough-ins on common area
- 3rd floor, rough-ins on common area
Masonry:
- 4th floor, block wall installation on elevator shaft, north-east and south-east airshafts
- 4th floor, block wall installation on stairwell 1 and 2
Drywall:
- Ground floor, fire rating beams and columns
- Ground floor, resilient channel installation
- 2nd floor, resilient channel installation
Sprinklers:
- P2 level, sprinklers system installation













Structural Steel:
- 3rd floor wall installation 75%
- 4th floor joists installation 80%
- 4th floor deck installation 30%
- 4th floor pour 01 concrete pouring 50%
Mechanical:
- Installation of the mechanical room 100%
- Ground floor HVAC installation 90%
- Ground floor plumbing installation 30%
Electrical:
- Rough-ins on the ground floor 70%
- Installation of equipment on the electrical room 90%
Masonry:
- 3rd floor stair 1 block wall installation 100%
- 3rd floor stair 2 block wall installation 100%
- 3rd floor block wall installation on the south-east side air shaft 100%
Drywall:
- Ground floor drywall installation around fan coils 20%
- 2nd floor resilient channel installation 60%
Sprinklers:
- P2 & P1 levels, sprinklers system measurements










Structural Steel:
- 3rd floor wall panel installation
- 4th floor joist installation
- 4th floor metal deck installation
- 4th floor metal deck installation
- 4th floor, pour 01, concrete pouring
Mechanical:
- P1, ongoing installation on mechanical room
- P1, installation of the sanitary lines
- GF, installation of duct work
- GF, plumbing installation
- Cooling tower installation
Electrical:
- P1 & P2, ongoing pulling wire and installing lighting
- P1, equipment installation at electrical room
- GF, ongoing installation of duct work
- GF, ongoing rough in
- 2nd floor, ongoing rough in at common area
Masonry:
- 3rd floor, masonry walls installation on stair 1
- 3rd floor, masonry walls installation on stair 2
- 3rd floor, masonry walls installation on south-east air shaft
Windows:
- GF, windows installation

Structural Steel:
- Balcony precast installation
- 3rd floor wall panel installation
- 4th floor joist installation
- 4th floor metal deck installation
Mechanical:
- P1, ongoing installation on mechanical room
- P1, installation of the sanitary lines
- GF, installation of duct work
Electrical:
- P1 & P2, ongoing pulling wire and installing lighting
- P1, working in mechanical room
- GF, rough in
- 2nd floor, rough in at common area
Masonry:
- 3rd floor, masonry walls installation on north-east air shaft
- 3rd floor, masonry walls installation on elevator shaft
Windows:
- 2nd floor – windows installation










Structural Steel:
- 3rd floor, pour 03 – Concrete pouring
- 3rd floor, pour 01 – wall panel installation
- 3rd floor, pour 03 – joist installation
- 2nd floor, balcony post installation
Mechanical:
- Ongoing installation on mechanical room
- Installation of duct work on GF
- Installation of the plumbing pipes on P1 by air shaft
- Installation of the sanitary lines on P1
- Running glycol lines that go under the ramp for the parking garage
Electrical:
- Pulling wire and installing lighting on P1
- Pulling wire and installing lighting on P2
Masonry:
- Marking out layout for shoring posts on second floor
- Installation of the shoring posts on GF under area of stair #1, air shaft and elevator shaft
- Masonry walls installation on 3rd floor
Misc. Metals:
- Completing remedial work on balcony posts on east elevation GF per SI 117R
Windows:
- 2nd floor – windows installation










Structural Steel:
- 3rd floor, pour 02 – Concrete pouring
- 3rd floor, pour 03 – wall panel installation
- 3rd floor, pour 03 – joist installation
- 3rd floor, pour 03 – metal deck installation
Mechanical:
- Ongoing installation on mechanical room
- Remedial work in the fire pump room
- Installation of duct work on GF
- Installation of sleeper beams
Electrical:
- Ongoing rough ins on Ground floor
- Pulling wire on P1 and GF
- Pulling wire and installing lighting on P2
Masonry:
- Block work at storage area at P2
- Block work at P1 by water pump room
- Installing door frames and block work on P1 for locker and storage room










Accordion Content
Structural Steel:
- 2nd Pour on 2nd floor slab
- Installation of joists and decking on Pours 05 and 06
- Installation of wall panels on pours 01 and 02
Mechanical:
- Installation of permanent water meter
- Ongoing work on mechanical room
Electrical:
- Ongoing installation of equipment on Electrical room and cables into the Electrical room
- Rough ins on Ground floor, where 2nd floor slab is poured
Masonry:
- Masonry walls on Pour 02 – airshaft and elevator hoistway