Construction Updates

Structural Steel:
  • Shelf angle installation
  • 4th floor, wall installation
Mechanical:
  • Ground floor, installation of sanitary lines
  • 2nd floor, installation of sanitary lines
Electrical:
  • 2nd floor, rough-ins on common area
  • 3rd floor, rough-ins on common area
Masonry:
  • 4th floor, block wall installation on elevator shaft, north-east and south-east airshafts
  • 4th floor, block wall installation on stairwell 1 and 2
Drywall:
  • Ground floor, fire rating beams and columns
  • Ground floor, resilient channel installation
  • 2nd floor, resilient channel installation
Sprinklers:
  • P2 level, sprinklers system installation

Structural Steel:
  • 3rd floor wall installation 75%
  • 4th floor joists installation 80%
  • 4th floor deck installation 30%
  • 4th floor pour 01 concrete pouring 50%
Mechanical:
  • Installation of the mechanical room 100%
  • Ground floor HVAC installation 90%
  • Ground floor plumbing installation 30%
Electrical:
  • Rough-ins on the ground floor 70%
  • Installation of equipment on the electrical room 90%
Masonry:
  • 3rd floor stair 1 block wall installation 100%
  • 3rd floor stair 2 block wall installation 100%
  • 3rd floor block wall installation on the south-east side air shaft 100%
Drywall:
  • Ground floor drywall installation around fan coils 20%
  • 2nd floor resilient channel installation 60%
Sprinklers:
  • P2 & P1 levels, sprinklers system measurements

Structural Steel:
  • 3rd floor wall panel installation
  • 4th floor joist installation
  • 4th floor metal deck installation
  • 4th floor metal deck installation
  • 4th floor, pour 01, concrete pouring
Mechanical:
  • P1, ongoing installation on mechanical room
  • P1, installation of the sanitary lines
  • GF, installation of duct work
  • GF, plumbing installation
  • Cooling tower installation
Electrical:
  • P1 & P2, ongoing pulling wire and installing lighting
  • P1, equipment installation at electrical room
  • GF, ongoing installation of duct work
  • GF, ongoing rough in
  • 2nd floor, ongoing rough in at common area
Masonry:
  • 3rd floor, masonry walls installation on stair 1
  • 3rd floor, masonry walls installation on stair 2
  • 3rd floor, masonry walls installation on south-east air shaft
Windows:
  • GF, windows installation

Structural Steel:
  • Balcony precast installation
  • 3rd floor wall panel installation
  • 4th floor joist installation
  • 4th floor metal deck installation
Mechanical:
  • P1, ongoing installation on mechanical room
  • P1, installation of the sanitary lines
  • GF, installation of duct work
Electrical:
  • P1 & P2, ongoing pulling wire and installing lighting
  • P1, working in mechanical room
  • GF, rough in
  • 2nd floor, rough in at common area
Masonry:
  • 3rd floor, masonry walls installation on north-east air shaft
  • 3rd floor, masonry walls installation on elevator shaft
Windows:
  • 2nd floor – windows installation

Structural Steel:
  • 3rd floor, pour 03 – Concrete pouring
  • 3rd floor, pour 01 – wall panel installation
  • 3rd floor, pour 03 – joist installation
  • 2nd floor, balcony post installation
Mechanical:
  • Ongoing installation on mechanical room
  • Installation of duct work on GF
  • Installation of the plumbing pipes on P1 by air shaft
  • Installation of the sanitary lines on P1
  • Running glycol lines that go under the ramp for the parking garage
Electrical:
  • Pulling wire and installing lighting on P1
  • Pulling wire and installing lighting on P2
Masonry:
  • Marking out layout for shoring posts on second floor
  • Installation of the shoring posts on GF under area of stair #1, air shaft and elevator shaft
  • Masonry walls installation on 3rd floor
Misc. Metals:
  • Completing remedial work on balcony posts on east elevation GF per SI 117R
Windows:
  • 2nd floor – windows installation

Structural Steel:
  • 3rd floor, pour 02 – Concrete pouring
  • 3rd floor, pour 03 – wall panel installation
  • 3rd floor, pour 03 – joist installation
  • 3rd floor, pour 03 – metal deck installation
Mechanical:
  • Ongoing installation on mechanical room
  • Remedial work in the fire pump room
  • Installation of duct work on GF
  • Installation of sleeper beams
Electrical:
  • Ongoing rough ins on Ground floor
  • Pulling wire on P1 and GF
  • Pulling wire and installing lighting on P2
Masonry:
  • Block work at storage area at P2
  • Block work at P1 by water pump room
  • Installing door frames and block work on P1 for locker and storage room

Accordion Content
Structural Steel:
  • 2nd Pour on 2nd floor slab
  • Installation of joists and decking on Pours 05 and 06
  • Installation of wall panels on pours 01 and 02
Mechanical:
  • Installation of permanent water meter
  • Ongoing work on mechanical room
Electrical:
  • Ongoing installation of equipment on Electrical room and cables into the Electrical room
  • Rough ins on Ground floor, where 2nd floor slab is poured
Masonry:
  • Masonry walls on Pour 02 – airshaft and elevator hoistway

CONDOMINIUMS

IN THE HEART OF

CATHEDRALTOWN

sales office hours

Schedule an Appointment

    I agree that my submitted data is being collected and stored.
    This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

    Wednesday: 12:00 pm – 4:00 pm
    Thursday: 12:00 pm – 4:00 pm
    Friday: 12:00 pm – 4:00 pm
    Saturday: 12:00 pm – 4:00 pm

    Get In Touch With

      I am interested in:
      How did you hear about us?
      Are you a Realtor? NOYES
      I agree that my submitted data is being collected and stored.
      This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

      Contact info

      HCRA Licence Certificate
      © 2016 King David Inc. All Right Reserved.