Construction Updates

Structural Steel:
  • Shelf angle installation
  • 4th floor, wall installation
Mechanical:
  • Ground floor, installation of sanitary lines
  • 2nd floor, installation of sanitary lines
Electrical:
  • 2nd floor, rough-ins on common area
  • 3rd floor, rough-ins on common area
Masonry:
  • 4th floor, block wall installation on elevator shaft, north-east and south-east airshafts
  • 4th floor, block wall installation on stairwell 1 and 2
Drywall:
  • Ground floor, fire rating beams and columns
  • Ground floor, resilient channel installation
  • 2nd floor, resilient channel installation
Sprinklers:
  • P2 level, sprinklers system installation

Structural Steel:
  • 3rd floor wall installation 75%
  • 4th floor joists installation 80%
  • 4th floor deck installation 30%
  • 4th floor pour 01 concrete pouring 50%
Mechanical:
  • Installation of the mechanical room 100%
  • Ground floor HVAC installation 90%
  • Ground floor plumbing installation 30%
Electrical:
  • Rough-ins on the ground floor 70%
  • Installation of equipment on the electrical room 90%
Masonry:
  • 3rd floor stair 1 block wall installation 100%
  • 3rd floor stair 2 block wall installation 100%
  • 3rd floor block wall installation on the south-east side air shaft 100%
Drywall:
  • Ground floor drywall installation around fan coils 20%
  • 2nd floor resilient channel installation 60%
Sprinklers:
  • P2 & P1 levels, sprinklers system measurements

Structural Steel:
  • 3rd floor wall panel installation
  • 4th floor joist installation
  • 4th floor metal deck installation
  • 4th floor metal deck installation
  • 4th floor, pour 01, concrete pouring
Mechanical:
  • P1, ongoing installation on mechanical room
  • P1, installation of the sanitary lines
  • GF, installation of duct work
  • GF, plumbing installation
  • Cooling tower installation
Electrical:
  • P1 & P2, ongoing pulling wire and installing lighting
  • P1, equipment installation at electrical room
  • GF, ongoing installation of duct work
  • GF, ongoing rough in
  • 2nd floor, ongoing rough in at common area
Masonry:
  • 3rd floor, masonry walls installation on stair 1
  • 3rd floor, masonry walls installation on stair 2
  • 3rd floor, masonry walls installation on south-east air shaft
Windows:
  • GF, windows installation

Structural Steel:
  • Balcony precast installation
  • 3rd floor wall panel installation
  • 4th floor joist installation
  • 4th floor metal deck installation
Mechanical:
  • P1, ongoing installation on mechanical room
  • P1, installation of the sanitary lines
  • GF, installation of duct work
Electrical:
  • P1 & P2, ongoing pulling wire and installing lighting
  • P1, working in mechanical room
  • GF, rough in
  • 2nd floor, rough in at common area
Masonry:
  • 3rd floor, masonry walls installation on north-east air shaft
  • 3rd floor, masonry walls installation on elevator shaft
Windows:
  • 2nd floor – windows installation

Structural Steel:
  • 3rd floor, pour 03 – Concrete pouring
  • 3rd floor, pour 01 – wall panel installation
  • 3rd floor, pour 03 – joist installation
  • 2nd floor, balcony post installation
Mechanical:
  • Ongoing installation on mechanical room
  • Installation of duct work on GF
  • Installation of the plumbing pipes on P1 by air shaft
  • Installation of the sanitary lines on P1
  • Running glycol lines that go under the ramp for the parking garage
Electrical:
  • Pulling wire and installing lighting on P1
  • Pulling wire and installing lighting on P2
Masonry:
  • Marking out layout for shoring posts on second floor
  • Installation of the shoring posts on GF under area of stair #1, air shaft and elevator shaft
  • Masonry walls installation on 3rd floor
Misc. Metals:
  • Completing remedial work on balcony posts on east elevation GF per SI 117R
Windows:
  • 2nd floor – windows installation

Structural Steel:
  • 3rd floor, pour 02 – Concrete pouring
  • 3rd floor, pour 03 – wall panel installation
  • 3rd floor, pour 03 – joist installation
  • 3rd floor, pour 03 – metal deck installation
Mechanical:
  • Ongoing installation on mechanical room
  • Remedial work in the fire pump room
  • Installation of duct work on GF
  • Installation of sleeper beams
Electrical:
  • Ongoing rough ins on Ground floor
  • Pulling wire on P1 and GF
  • Pulling wire and installing lighting on P2
Masonry:
  • Block work at storage area at P2
  • Block work at P1 by water pump room
  • Installing door frames and block work on P1 for locker and storage room

Accordion Content
Structural Steel:
  • 2nd Pour on 2nd floor slab
  • Installation of joists and decking on Pours 05 and 06
  • Installation of wall panels on pours 01 and 02
Mechanical:
  • Installation of permanent water meter
  • Ongoing work on mechanical room
Electrical:
  • Ongoing installation of equipment on Electrical room and cables into the Electrical room
  • Rough ins on Ground floor, where 2nd floor slab is poured
Masonry:
  • Masonry walls on Pour 02 – airshaft and elevator hoistway

CONDOMINIUMS

IN THE HEART OF

CATHEDRALTOWN

sales office hours

Schedule an Appointment

    I agree that my submitted data is being collected and stored.
    This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

    Wednesday: 12:00 pm – 4:00 pm
    Thursday: 12:00 pm – 4:00 pm
    Friday: 12:00 pm – 4:00 pm
    Saturday: 12:00 pm – 4:00 pm

    Get In Touch With

      I am interested in:
      How did you hear about us?
      Are you a Realtor? NOYES
      I agree that my submitted data is being collected and stored.
      This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
      © 2016 King David Inc. All Right Reserved.